The team is inching closer to finishing the foundation for more than half of the buildings in Phase 1 of the plan.

Updates From Owner’s Rep: Week 2

  • All geodesic work is completed.
  • Installing the fence along the borders of the plot.
  • Dug out two pits for 16-plexes. Started preparing everything to pour concrete and forming the basement/shelter area. We will be adding stiffening and adding the blocks.
  • One of the 8-plexes has a completed foundation, the second one (out of 4) has nearly completed foundation as well. We started installing the plumbing into of them.
  • Starting work on the other two 8-plexes.
  • Six of the duplexes have nearly finished foundations. We are finishing the formwork. We are starting work on the remaining three duplexes and their foundations.
  • The plot now has electricity.
  • The first water well is completed and starting drilling the second well.
  • All the roads have been marked.
  • Preparing spot for the water tower along with water filtration system.

Videos From Week 2:

Foundation Digging for 16-plexes:

Installing Fence Around The Plot

Drilling The First Water Well

Foundation Digging in 16-plex: Close-up

Preparing to Pour Concrete Into 6 Duplexes

Finishing the Foundation on The First 8-Plex: Preparing The Plumbing

Finished Foundation With Plumbing for The 8-Plex and Drilling a Second Water Well (June 6)